New building strategic extension of the IHP clean room (STRE)

New building strategic extension of the IHP clean room (STRE)

New building strategic extension of the IHP clean room (STRE)

The clean room - the technological heart of the Leibniz Institute for High Performance Microelectronics in Frankfurt (Oder) was extended by half in just 2.5 years of construction and continues to set the IHP on a course towards leading microelectronic solutions of the future.

The extension of the clean room area to the size of 1500 square meters, on one hand, enables the IHP to provide scientific and research partners with a stable BiCMOS technology platform and, on the other hand, to research the possibilities of new materials. The goal is to be able to set records such as the world’s fastest silicon-germanium transistor in the future as well. The new metallization system, which has already been purchased within the framework of the Research Factory Microelectronics Germany, is the basis for the planned exploratory clean room in the newly built part of the building and should enable future work with new, high-performance contact materials.

In addition, the space gained is being used for the continuous modernization of the ultra-modern pilot line, which operates on a 24/7 basis to prototype the integrated circuits of the future.

Press release: 2021-03-04

 

 

Funding

This project was supported by funding from the state of Brandenburg, the federal government and the European Union.

Awarding Authority

Investitionsbank des Landes Brandenburg (ILB)
Babelsberger Straße 21
14473 Potsdam

General planning:     

HENN GmbH, Alexanderstraße 7, 10178 Berlin

Project control:        

Bauplanung Stoessel GmbH, Budapester Straße 31, 10787 Berlin

Special challenge

Construction during the continuous operation of the existing clean room

Key facts:

Additionally usable clean room area 500 m2
Gross floor area 3800 m2
Gross volume 18200 m2
Length x Width 27 m x 35 m

Schedule

Presentation of the project idea 2017-05                     
Submission of building application 2018-05
Building permit 2018-09-05
Laying of the foundation stone 2018-09-08
Start of shell 2019-03
Ready for Equipment 2020-09-30
Usage of the building 2020-12
Remaining services 2021

Special challenge

Construction during the continuous operation of the existing clean room

Key facts:

Additionally usable clean room area 500 m2
Gross floor area 3800 m2
Gross volume 18200 m2
Length x Width 27 m x 35 m

Schedule

Presentation of the project idea 2017-05                     
Submission of building application 2018-05
Building permit 2018-09-05
Laying of the foundation stone 2018-09-08
Start of shell 2019-03
Ready for Equipment 2020-09-30
Usage of the building 2020-12
Remaining services 2021